Safety 1st Advancer Manuel de l'opérateur Page 58

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 132
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 57
Environmental Remediation Drilling
Safety Guideline
Page 58 of 132
4.5.14 - Underground utilities
Complete utility locates prior to drilling [One Call: 811 or your local utility locating service] and
coordinate with the drilling contractor and site personnel.
Mark locations in white
Field verify utility locations
Document all utility locates on a plot plan or other map of the site.
Observe the area for indications of utilities
Hand dig if questions remain or if required by the property owner
Refer to your specific Utility Clearance and Isolation procedure
4.5.15 - Environmental Contamination (if applicable)
Before Visqueen or other plastic is laid down, the site will be cleared of trip hazards, obstacles or debris
such as rocks, sticks, ruts and holes.
Contain cuttings in drums or plastic sheeting
Wear proper PPE and minimize contact with soil, sediment, groundwater, or other contamination.
Work upwind of the boring
If unusual soil discoloration or odors are encountered, stop work, evacuate area and contact the safety
manager. The approach will need to be re-evaluated and a PPE upgrade may be required
Follow all provisions of the Health and Safety Plan
4.5.16 - Working on Streets or Highways
Follow state and local laws concerning traffic control signage, cones, and barricades.
Do not work before sun-up, after sundown, or any time visibility is poor.
Position support vehicle(s) between the work area and oncoming traffic.
Use safety strobe lights on all vehicles and equipment.
Wear appropriate reflective safety vests.
Use radios when flagging.
Vue de la page 57
1 2 ... 53 54 55 56 57 58 59 60 61 62 63 ... 131 132

Commentaires sur ces manuels

Pas de commentaire